2012-11-16 - 5360 - Service Request - PrePack Confirmations #US #ProductionBreakFix #ProductionOrders #Routings

5360 - Pre-Packs Confirmations

Summary Description


Pre-Pack Production Orders showing PCNF for fully delivered orders.

Admin Info



Title
5360 - Pre-Pack Confirmations
Requested by
Rahul
Issue Date
12-21-2012
Resolved by
Adithya
Resolved Date
11-16-2012
Status
Complete

Detailed Description

(Include Screen Shots if required )

Pre-Packs Production Orders showing PCNF for fully delivered orders. The default confirmation type in CO11N is “Automatic Final Confirmation”. In order to make it go to CNF you have to manually choose “Final Confirmation “from a drop down. Why do these orders behave differently than any other one? When running reports in COOIS, this less than final confirmation is confusing.

Analysis and Recommendations

(Include Screen Shots if required)

It was observed that the order quantity is 52 and operation quantity is 318.

PrePack-1.png

PrePack-2.png
In confirmation we see that the planned total qty is 318 P6, and yield is 53, Hence the status is PCNF.

PrePack-3.png

The unit in Operation Quantity must be EA instead of P6, which should be 318 EA.
A Pre-Pack is a one pack with 6 EA, which makes 53 P6 as 318 EA.

"1 P6 = 6 EA"

Below are the steps:
If we need the quantities as EA in Operation then we hane maintain routing as shown,

1. Maintaining P6 at Routing Header.
PrePack-4.png

2. At operation level the conversions in routing must be maintained as shown in below screen shot.
PrePack-5.png

Test:
we can have a look at Production order 1000240244 for Test,
PrePack-6.PNG
at operation level in Production order
Pre-Pack7.PNG

Resolution


Sent the document to client and the changes were done to existing Routing.

Release Information


Provide link here to Release Notes